From new SWD facilities to expanding our gathering pipeline network — Henry Hill continues to invest in the infrastructure that keeps Williston Basin production moving.

Recent & Notable Projects

Henry Hill is a midstream owner-operator. Every project below represents infrastructure we built and continue to own and operate — not work handed off at completion, but facilities we stand behind for the long term.

Completed Projects
SWD Complete 2024

McKenzie County SWD Capacity Upgrade

Major throughput upgrade at our McKenzie County disposal facility, including new high-capacity injection pumps, expanded tank storage, and a full SCADA integration upgrade. The project significantly increased disposal capacity to meet growing demand from area producers.

New injection pump skids installed and commissioned
Additional produced water storage tankage added
SCADA control system upgraded with new RTU hardware
Facility fully integrated into Central Monitoring Station
McKenzie County, ND SWD Expansion SCADA Integrated
SCADA Completing Q1 2026

Central Monitoring Station Technology Upgrade

Major upgrade of our Central Monitoring Station infrastructure, including a new SCADA software platform, upgraded communication hardware across all field sites, and expanded camera monitoring coverage. The upgrade brings all facilities under a unified monitoring and control interface with improved alarm management and historical data logging — completing Q1 2026.

New SCADA platform deployed at Central Monitoring Station
Field RTU hardware upgraded at all SWD facilities
Live camera feeds added at additional sites
Automated alarm escalation and on-call system: Completing Q1 2026
Williston, ND (HQ) SCADA / Technology All Facilities
Upcoming & In Progress
Pipeline In Progress Ongoing 2026

McKenzie County Pipeline Network Expansion

Henry Hill continues to grow its gathering pipeline footprint across McKenzie County. Two new production sites were successfully brought online in Q4 2025, adding pipeline-connected disposal capacity for additional operators in the area. Further tie-ins are planned for Q1 and Q2 2026, with additional third-party offload agreements in place to expand total system throughput beyond our owned injection capacity.

2 new production sites tied in and commissioned: Q4 2025
Additional wellpad connections: Q1 2026
Further gathering lateral extensions: Q2 2026
3rd-party offload agreements active — expanding disposal capacity
McKenzie County, ND Gathering Pipeline Ongoing Expansion
SCADA Planning Est. Q4 2026

Full-Network Camera Monitoring Expansion

Expansion of on-site camera coverage to achieve 100% visual monitoring across every facility in our network. This project will complement our existing SCADA instrumentation with full live video feeds at all sites, integrated into our Central Monitoring Station and accessible by our NOC team around the clock.

Camera hardware specification and procurement: In Progress
Network communication upgrades at remaining sites: Q3 2026
Camera installation and commissioning: Q4 2026
Central Monitoring Station display upgrade: Q4 2026
All Network Facilities Camera / SCADA Full Network Coverage